BUILDING ON YOUR PROPERTY - BUILDING LAWS
OF COSTA RICA
Before
you purchase a lot with the intent of building
on it, you should conduct some preliminary studies
on the property to ensure that there won't be
a problem obtaining a building permit. First,
determine if the lot has basic services such
as water, electricity, telephone, and drainage.
Second, make sure there are no restrictions
placed on the lot that could result in the denial
of a construction permit. It will not be enough
to check the Public Registry. You should also
check the Ministry of Public Works (Ministerio
de Obras Públicas y Transporte) for future
road construction projects; the Ministry of
Health (Ministerio de Salud); the National Institute
of Housing and Urban Development (Instituto
Nacional de Vivienda y Urbanismo) and the municipality
where the property is located (municipalidad).
And finally, be aware of any environmental regulation
that may affect your construction project, such
as national wildlife refuges and areas deemed
protected by the forestry Law.
Requests
for construction permits are filed with the Permit
Reception Office (Oficina Receptora de Permisos
de Construcción), which is a centralized
office that houses government representatives
from MOPT (Ministerio de Obras Públicas
y Transportes-roads), INVU (Instituto Nacional
de Vivienda y Urbanismo-housing), ICE (Instituto
Costaricense de Electricidad-telephone), AYA (Instituto
Costaricense de Acueductos y Alcantarillados-water),
SNE (Servicio Nacional de Electricidad-electricity),
CFIA (Colegio Federado de Ingenieros y Arquitectos),
and the Ministry of Health (Ministerio de Salud).
For a single family home that measures more than
70 m2 (735.2 ft.2), the applicant must provide
the following documentation: four copies of the
construction plans, four copies of the property
cadastre plot plan (Plano catastrado), four copies
of the permit checklist (hoja de comisión),
two copies of your property deed (escritura),
one copy of the consulting contract with your
architect/engineer (contrato de consultoria),
an approval from the water company (AYA) regarding
availability of water, and one copy of your electrical
design plan approved by SNE. Condominium projects,
commercial construction, and urbanization projects
all carry additional requirements for obtaining
construction permits.
In addition to these requirements, you will need
to request a building permit from the municipality
in which the property is located. By law it is
the municipality that is delegated the responsibility
to ensure that all constructions comply with building
regulations (Article 1, Construction Law). You
can, therefore, expect periodic visits to your
construction site by the municipal building inspector,
who must certify that the construction is proceeding
according to code.
Whether you purchase an existing property or decide
to build you dream home, be well informed about
the procedures involved so that you ensure your
investment will be a profitable one.
All architects and engineers in Costa Rica must
be licensed by the Costa Rican Association of
Engineers and Architects (Colegio Federado de
Ingenieros y Ingenieros y Arquitectos-CFIA. This
governing body establishes the fee schedule that
can be charged by its members. Most fees are based
upon a percentage of the value of the construction
project. According to the regulations of the CFIA
(Reglamento para la Contratación de Servicios
de Consultoría en Ingeniería y Arquitectura),
the involvement of a licensed architect/engineer
in a construction project is separated into two
phases. Phase 1 is construction plans and permits,
and phase 2 is control and execution.
In order to build in Costa Rica, you will likely
face a bureaucratic maze of governmental regulations.
The law requires that any application for a construction
permit be presented by a licensed architect or
engineer (Article 83, Law of Constructions, Article
II.2 Construction Regulations). It is therefore
advisable to contact a reputable, licensed architect
or civil engineer to guide you through the construction
process.
All architects and engineers in Costa Rica must
be licensed by the Costa Rican Association of
Engineers and Architects (Colegio Federado de
Ingenieros y Ingenieros y Arquitectos-CFIA. This
governing body establishes the fee schedule that
can be charged by its members. Most fees are based
upon a percentage of the value of the construction
project. According to the regulations of the CFIA
(Reglamento para la Contratación de Servicios
de Consultoría en Ingeniería y Arquitectura),
the involvement of a licensed architect/engineer
in a construction project is separated into two
phases. Phase 1 is construction plans and permits,
and phase 2 is control and execution
Phase 1 - Construction Plans
and Permits: This phase is further subdivided
into several distinct professional services that
can be provided to the client by the architect/engineer.
The percentages cited below are those that the
CFIA has established as minimum chargeable fees.
A.
Preliminary studies (estudios preliminaries):
0.5 percent. These studies may or may not be
required, depending on the scope of the project.
B. Pre-project design (anteproyecto): 1.0 to
1.5 percent. Generally, during this stage, the
architect/engineer will meet with the client
in order to discuss the client's construction
requirements. With this information, the architect/engineer
will prepare drafts of the proposed construction
project for review by the client. These drafts
should include site planning and preliminary
work drawings. When you contract for this service
be sure you agree with your architect/engineer
beforehand on what he or she is going to provide
you.
C. Construction plans and technical specifications
(planos de construcción y especificaciones
técnicas): 4.0 percent. This is one of
the most important steps in the overall construction
project since execution of the project will
depend upon the quality and accuracy of your
construction plans. Once you and your architect/engineer
have agreed on the layout and design of the
project, she or he will begin drafting the plans.
In Costa Rica, a complete set of plans should
include a site plan, distribution plan, elevation
and transversal and longitude perspectives,
roof design and drainage, design of footings
and support beams, structural plans, electrical
design, mechanical and sanitary system design,
as well as a plan that details all of the interior
finishing's of the construction. Budgeting (presupuesto):
0.5 percent for global budgeting; 1.0 percent
for itemized budgeting. Here the architect/engineer
prepares a materials list based upon your construction
plans and prepares a construction budget for
you.
Phase 2 - Control and Execution.
This stage involves the actual construction and
project supervision. The regulations authorize
three kinds of supervisory tasks, each of which
requires a larger time investment from the architect/engineer.
Inspection (Inspección): 3 percent of total
construction value. Here your architect/engineer
will visit the construction site at least once
a week and will inspect it to ensure that the
plan specifications are being followed by the
general contractor. They will also verify the
quality of the materials being used and review
invoices being presented by the general contractor.
A.
Supervision (Dirección Técnica):
5 percent. This requires more direct involvement
by the architect/engineer in the day-to-day
operation of the project.
B. Administration (Administración):
12 percent. Here, the architect/engineer takes
complete responsibility for the execution and
completion of the project.
The option you choose will depend upon the type
of project involved, the reliability of your builder/general
contractor, and the amount of time you are willing
to dedicate to the construction project. All told,
phases 1 and 2 can range from 9 percent to 18
percent of the estimated value of the construction
project, depending on the amount of services required.
As such, it is common practice to negotiate fees
with the architect/engineer. Most, of course,
will be eager for your business and, depending
on the scope of the project will be willing to
work out an agreement tailored to your particular
needs. Otherwise, have your attorney do the negotiating
for you to ensure that you will get the best agreement
possible.
Before you sign any contract, be sure that you
understand the fee structure and know exactly
what is and is not included in the fee. Likewise,
clearly define the responsibilities that your
architect/engineer is going to assume. Do the
same thing with your general contractor and any
subcontractors.
Hiring an Architect or Civil Engineer
By law, all applications for construction permits
must be filed by an architect or civil engineer
who is a member of the Costa Rican Association
of Engineers and Architects (Colegio Federado
e Ingenieros y Arquitectos). These experts will
review your plans to ensure the building meets
seismic, electrical and other regulations standards.
How much does an Architect cost?
Here are the minimum rates charged by members
of the Costa Rican Association of Engineers and
Architects:
Preliminary study of construction plans and permits:
0.5% of project cost. (Such a study may or may
not be required, depending on the project.)
Pre-project design: 1% to 1.5%
of the price of project cost.
If the architect meets with you to discuss your
needs, provides you with drafts of site planning,
reviews construction plans and technical specifications
of the project: 4.0% of project cost.
Once you have agreed with the layout and design
of the property, the architect will draw up the
plans. These will include a site plan, distribution
plan, elevation and transversal and longitude
perspectives, roof design and drainage, design
of footings and support beams, structural plans,
electrical design, mechanical and sanitary system
design, interior finishing and construction. He
will provide you with a list of materials necessary
for the project, and will prepare a construction
budget.
Figure 0.5% of project cost for global budgeting;
1.0% for itemized budgeting.
Control and Execution
Construction and project supervision
Regulation require one of three types of supervision
A. Inspection: The engineer or
architect visits the site once a week, inspects
to make sure that the plan is being followed by
the general contractor, informs you of the quality
of materials being used, and checks the invoices
submitted by the general contractor. Cost: 3%
of total construction costs.
B. Supervision: Engineer or architect
visits your site daily and is more directly involved
with the construction. Cost: 5% of total construction
costs.
C. Management: Engineer or architect steps in
to manage the project. Cost: 12% of total construction
costs.
Before signing any of these contracts make sure
that you have a thoroughly understanding its contents.
Hearts are broken less by malice than by miscommunication.
Getting
a Building Permit
You must get a construction permit to build a
house of more than 70 sq./m. (750 sq./ft.)
You or your architect must file for permits at
the Oficina Receptora de Permisos de Construccion
(Permit Reception Office). The plans will be studied
by representatives from the MOPT (Roads and Transportation
Department), INVU (Housing and Urban Development
Department), ICE (Electricity Department), AYA
(Water Department), SNE (National Electrical Services),
CFIA (Costa Rican Architect and Engineer Association),
the Health Department and the local municipality
where the property is located.
You will need the following:
1.
Four copies of the construction plans
2. Four copies of the property cadastre plan
(plano catastrado)
3. Two copies of the property deeds
4. One copy of the architect or engineer's consulting
contract (Contrato de Consultoria)
5. Approval from the water department regarding
availability of water
6. One copy of your electrical design plan approved
by SNE.
Note:
Condominium, commercial construction or urbanization
projects require additional permits.
Local
Building Permits
NOTE BENE: In addition to the permits listed above,
you will need a construction permit from the municipality
where your property is located. Each municipality
creates and enforces building codes for construction
project in its area.
How Long Is This Going To Take?
Property research, first draft 6 1/2 weeks
Construction plans 6 1/2 weeks
Building permits 9 weeks
Construction 33 weeks
Total: 55 weeks
The Total Cost
Building a house in Costa Rica is going to cost
about $315 to $540 per sq. meter ($29 to $50 sq./f.)
depending on the quality of work and materials.
So, consult your calculator and you discover that
you can build a home large enough to lie down
in without hanging your feet out the window (say,
10 by 20 m., or 32 by 64 ft.) for $73,000 to $108,000,
not counting land costs. By European or North
American standards, that's quite a bargain price,
especially if your new home is built on a palm-studded
hillside, bathed by tropical breezes, perfumed
by sea air with no snow to shovel. Then the price
seems a bargain, indeed.
Here Are a Few House Building Tips
A. Check for neighborhood zoning laws. In order
to maintain local standards (and property values)
some locales set down strict rules for style
and quality of construction.
B. You cannot built a house within 50 to 100
meters (164 ft. to 328 ft.) of a river.
C. In most locales, you must to leave space
for a front yard and a sidewalk.
D. Housing developers keep in mind that Costa
Rican law allows you to dedicate only 60 to
70% of your land to be used for building lots.
20% to 25% will be used for property for roads
and 5% to 20% for parks.
E. If you have a nice view from your property,
play it smart. Buy the land around it.
F. Contractors get a discount on materials.
It is always a temptation to build with the
stuff that gives them the best markup. Check
up on them. Make sure they're using the materials
agreed upon.
G. Along both coasts, the first 200 meters (656
ft.) above mean high tide is owned by the government.
No building is permitted within the first 50
meters (164 ft.) above mean high tide.
H. The area 50 meters(164 ft.) to 200 meters
(656 ft.) above mean high tide may be leased
from the local municipality with the approval
of the Instituto de Turismo (Costa Rican Tourist
Board). Ostensibly, foreigners cannot, legally
lease property in this area. However, a clever
or desperate person can find ways to circumvent
these laws.
I. The ICT discourages the building of anything
over three stories high in beach areas
|